Number the NFPA's steps for de-energizing equipment to place them in the correct order.
A. Perform lockout/tagout
B. Discharge and/or block any remaining stored energy before working on equipment
C. Turn off all energized components and disconnect all power sources
D. Test circuits with an appropriately-rated voltage meter
E. Locate all power sources
F. Release all stored electrical energy and release or block stored mechanical energy

Asked by hectormelendez21

Answer (2)

The NFPA's steps for safely de-energizing equipment must be followed in a specific order to ensure worker safety. The correct sequence includes locating power sources, disconnecting them, performing lockout/tagout procedures, and testing circuits. Adhering to these guidelines is critical in preventing electrical accidents during maintenance work. ;

Answered by GinnyAnswer | 2025-07-07

The NFPA's steps for de-energizing equipment should be followed in a specific order for safety. The correct sequence begins with locating power sources and ends with testing circuits with a voltage meter. Adhering to these guidelines significantly reduces the risk of accidents during maintenance tasks.
;