THE CONCRETE MIXED AND DELIVERED BY A MIXING TRUCK MUST BE DELIVERED AND DISCHARGED BEFORE THE DRUM HAS REVOLVED 300 TIMES.
True
False

Asked by matthewmenjarez

Answer (1)

The claim that concrete must be delivered before the drum has revolved 300 times is true, as this ensures the integrity and workability of the mix. If the mix is delayed beyond this point, the concrete can begin to set, leading to quality issues. Timely delivery is essential in the concrete industry to uphold standards. ;