Your team has been working hard on creating a new stakeholder engagement strategy which needs to be rolled out as soon as possible. You have been tasked with producing the project plan for implementing the strategy. Once you have done this, you are due to present the plan to your team and the project will officially start. One of your colleagues tells you that he has produced a plan for a similar project in the past. He thinks that it is likely that you can use the same timeline he proposed for his plan last year.

Rate the effectiveness of the following actions that you could take:

1. Ask for more detail about the project he produced the plan for so you can assess what the similarities are and what might be different.
Options: Counterproductive, Ineffective, Fairly Effective, Effective

2. Ignore the information your colleague has offered you and focus on creating your own plan which is completely relevant to this particular strategy implementation.
Options: Counterproductive, Ineffective, Fairly Effective, Effective

3. Ask other colleagues in your team if any of them have created similar project plans before so that you can use these to create yours as quickly as possible.
Options: Counterproductive, Ineffective, Fairly Effective, Effective

4. Re-use the project plan your colleague created, with limited changes, so you can present it to your team as quickly as possible.
Options: Counterproductive, Ineffective, Fairly Effective, Effective

Asked by cornpops1641

Answer (2)

The most effective actions include seeking more information from colleagues about past similar projects and consulting multiple team members for input. Ignoring advice or reusing an outdated plan without customization is counterproductive. A collaborative and informed approach will help create a robust and relevant project plan.
;

Answered by Anonymous | 2025-07-04

When you're tasked with producing a project plan for implementing a new stakeholder engagement strategy, it's essential to evaluate different actions you can take. Here's an assessment of the effectiveness of each action:

Ask for more detail about the project he produced the plan for so you can assess what the similarities are and what might be different.

Rating : Effective
Reason : Understanding the specifics of your colleague's previous project can provide valuable insights and help you identify similarities and differences. This helps in customizing the timeline and ensuring it's relevant to the new strategy, potentially saving time and effort while tailoring important details specific to your project's needs.


Ignore the information your colleague has offered you and focus on creating your own plan which is completely relevant to this particular strategy implementation.

Rating : Ineffective
Reason : Creating a plan without considering previous similar projects can lead to missing out on useful insights and proven solutions. While focusing on relevance is important, disregarding potentially helpful information is not efficient.


Ask other colleagues in your team if any of them have created similar project plans before so that you can use these to create yours as quickly as possible.

Rating : Fairly Effective
Reason : Gathering various inputs from multiple colleagues can give a broader perspective and may offer several successful strategies. However, it might lead to information overload and confusion if not managed properly.


Re-use the project plan your colleague created, with limited changes, so you can present it to your team as quickly as possible.

Rating : Counterproductive
Reason : Directly using last year's plan without significant adjustments might overlook key differences in objectives, stakeholders, and current project specifics. This approach can lead to potential issues during implementation and might not effectively engage stakeholders in the new strategy.



Overall, the key is balance: leveraging past experiences while ensuring the plan aligns specifically with the new project's goals and current circumstances.

Answered by SophiaElizab | 2025-07-06